Lyle Creek Data Center "Project Agate":data center in Conover, North Carolina.

Lyle Creek Data Center "Project Agate" is an under construction data center in Conover, North Carolina, listed under Microsoft. Planned capacity is 448 MW. Real Assets links 2 source pages, including Microsoft Local (Lyle Creek datacenter construction update), Data Center Dynamics.

Open this site on the map Start a 7-day trial
448 MWplanned capacity
Under constructionstatus
2source pages linked
Not recordedexpected completion

Facts on record

  • OperatorMicrosoft
  • City and stateConover, North Carolina
  • Statusunder construction
  • Planned capacity448 MW
  • Operating capacity todayNot recorded
  • Land area89 hectares (about 220 acres)
  • Building floor areaNot recorded
  • Expected completionNot recorded
  • Sources linked2 from 2 publishers
  • Record updated25 October 2026

Not recorded means no source states it. Real Assets does not fill a gap with an estimate.

Where it sits

North Carolina has 23 data centers on record in Real Assets, with 91 MW reported as operating and 3.95 GW not yet operating. Lyle Creek Data Center "Project Agate" is one of them.

Microsoft has 22 data centers on record in the United States: 10 operating and 12 planned or under construction.

Counts are sites Real Assets has recorded, not a full census, and grow as coverage grows. Data updated 25 October 2026.

Sources: the pages that published these facts

2 sources on record. The links open the original pages, not copies. How the data is built and what a source line means.

More Microsoft data centers in North Carolina

Microsoft data centers in other states

Other data centers in North Carolina

Full market dataset & site-level records

Open Lyle Creek Data Center "Project Agate" and 677 other data centers

This page is the public summary. Start a 7-day trial or sign in to see Lyle Creek Data Center "Project Agate" on the map with its exact location, every sourced figure and the filings behind it.

  • Every individual site on the interactive map with coordinates
  • Operating vs. pipeline capacity, operator and owner records
  • Sourced M&A, lease and financing transactions
  • Direct link to the filing, report or news page behind every figure
or unlock with work email

7-day free trial or subscription required for full site-level data. Instant sign-in with no password.

Questions

Who operates Lyle Creek Data Center "Project Agate"?

Lyle Creek Data Center "Project Agate" is recorded under Microsoft. The operator is the name its sources give, which can differ from the owner or the tenant.

Where is Lyle Creek Data Center "Project Agate"?

In Conover, North Carolina. This page does not publish a street address or map coordinates; the workspace shows the location on the map.

How much power does Lyle Creek Data Center "Project Agate" have?

448 MW. The site is not operating yet, so this is a stated plan, not delivered capacity. Operating capacity today is not recorded.

Where does this information come from?

From 2 linked pages by Microsoft Local (Lyle Creek datacenter construction update), Data Center Dynamics. Every link on this page goes to the original page. Anything not published there shows as not recorded, never as an estimate.