← Europe data centers · All sites
Sourced site record, every fact links to its page
Microsoft Spata data center:data center in Spata, Greece.
Microsoft Spata data center is an under construction data center in Spata, Greece, listed under Microsoft. Capacity is not recorded. 2024 to 2026 satellite: 2024 vs 2026 imagery. Real Assets links 1 source page, including Naftemporiki.
Open this site on the map View the full site recordunder construction data center · 1 linked source
- Microsoft
- Spata
- Greece
Approximate position and Greece peer sites (the exact position needs sign-in)
Facts on record
- OperatorMicrosoft
- City and countrySpata, Greece
- Statusunder construction
- Planned capacityNot recorded
- Expected completionNot recorded
- 2024 vs 2026 satelliteDated 2024 and 2026 passes, (2024 to 2026), 5 January 2024 to 18 October 2026
- Sources linked1 from 1 publisher
- Record updated17 November 2026
- 2024 vs 2026 satellite curtain slider🔒 Compare before and after
- Exact location on the map🔒 View on the map
Not recorded means no source states it. Real Assets does not fill a gap with an estimate.
Where it sits
Real Assets records 6 data centers in Greece that have a page.
Microsoft has 7 data centers on record in Europe: 0 operating and 7 planned or under construction.
Counts are sites Real Assets has recorded, not a full census, and grow as coverage grows. Data updated 19 November 2026; this page was built on 22 November 2026 at 12:21 UTC, so the live app can show a few more or fewer sites and deals.
Sources: the pages that published these facts
- Microsoft: Works in Spata and Paiania are advancing Skip to main content Αγορές Χρηματιστ
Naftemporiki, naftemporiki.gr, published 30 January 2025Web page
1 source on record. Public links open the original pages. How the data is built and what a source line means.
2024 vs 2026 satellite construction check
Dated 10 m satellite passes are stored for Microsoft Spata data center (5 January 2024 to 18 October 2026) for before-and-after comparison in the workspace.
Open 2024 vs 2026 satellite slider · All Europe 2024 vs 2026 satellite-tracked sites
Microsoft data centers in other countries
- Amsterdam data centre, Sloterdijk district
Amsterdam, Netherlands, plannedNot recorded - Microsoft AMS13/14 Middenmeer
Middenmeer, Netherlands, under constructionNot recorded - Microsoft Aragon La Muela Campus (Centrovía)
La Muela, Spain, plannedNot recorded - Microsoft Aragon Puerto Venecia Campus
Zaragoza, Spain, plannedNot recorded - Microsoft Aragon Villamayor de Gállego Campus
Villamayor de Gállego, Spain, under constructionNot recorded - Microsoft Madrid Data Center Campus
San Sebastián de los Reyes, Spain, plannedNot recorded
Other data centers in Greece
- DATA4 Athens Paiania Campus
Paiania, Greece, planned90 MW - Digital Realty ATH2
Athens, Greece, operatingNot recorded - Digital Realty ATH3
Athens, Greece, operatingNot recorded - Digital Realty ATH5
Athens, Greece, plannedNot recorded - Digital Realty Heraklion HER1
Heraklion, Greece, plannedNot recorded
Full site dossier & Europe dataset
Open Microsoft Spata data center and 500 other data centers
This page is the public summary for Microsoft Spata data center in Spata, Greece. Sign in to see its full record: 1 source page.
- Microsoft Spata data center on the interactive map, with the sites around it
- All 1 linked source page
A subscription opens full site-level data; the 3-day preview shows 20 sites. Instant sign-in with no password.
Free weekly market briefing
Not ready for the preview? Get the weekly email update
Once a week: new deals, primary filings and capacity changes recorded in this market. Free, with one-click unsubscribe.
Questions
Who operates Microsoft Spata data center?
Microsoft Spata data center is recorded under Microsoft. The operator is the name its sources give, which can differ from the owner or the tenant.
Where is Microsoft Spata data center?
In Spata, Greece. This page does not publish a street address or map coordinates; the workspace shows the location on the map.
How much power does Microsoft Spata data center have?
No capacity figure is recorded for this site. Real Assets does not estimate one.
Is Microsoft Spata data center under construction or growing on satellite imagery?
Dated 10 m satellite passes are stored for Microsoft Spata data center (5 January 2024 to 18 October 2026) for before-and-after comparison in the workspace.
Where does this information come from?
From 1 linked page by Naftemporiki. Every link on this page goes to the original page. Anything not published there shows as not recorded, never as an estimate.