← Europe data centers · All sites · Denmark
Sourced site record, every fact links to its page
Dansk Data Center 1 (DDC1) Esbjerg:data center in Esbjerg, Denmark.
Dansk Data Center 1 (DDC1) Esbjerg is an under construction data center in Esbjerg, Denmark, listed under Thylander. Planned capacity is 11.5 MW according to DCD. 2024 to 2026 satellite: 2024 vs 2026 imagery. Real Assets links 1 source page, including DCD.
Open this site on the map View the full site recordunder construction data center · 1 linked source
- Thylander
- Esbjerg
- Denmark
Approximate position and Denmark peer sites (the exact position needs sign-in)
Facts on record
- OperatorThylander
- City and countryEsbjerg, Denmark
- Statusunder construction
- Planned capacity11.5 MW, as stated by DCD
- Expected completionNot recorded
- 2024 vs 2026 satelliteDated 2024 and 2026 passes, (2024 to 2026), 29 April 2024 to 7 November 2026
- Sources linked1 from 1 publisher
- Record updated18 November 2026
- 2024 vs 2026 satellite curtain slider🔒 Compare before and after
- Exact location on the map🔒 View on the map
- Deals recorded on this site🔒 1 deal
Not recorded means no source states it. Real Assets does not fill a gap with an estimate.
Where it sits
Denmark has 11 data centers on record in Real Assets, with 23.7 MW reported as operating and 261.5 MW not yet operating. Dansk Data Center 1 (DDC1) Esbjerg is one of them.
Thylander has 1 data center in Europe with a page.
Counts are sites Real Assets has recorded, not a full census, and grow as coverage grows. Data updated 19 November 2026; this page was built on 22 November 2026 at 12:21 UTC, so the live app can show a few more or fewer sites and deals.
Sources: the pages that published these facts
- Thylander breaks ground on Danish data center in Esbjerg
DCD, datacenterdynamics.com, published 12 November 2026Web page
1 source on record. Public links open the original pages. How the data is built and what a source line means.
The full site record
Open Dansk Data Center 1 (DDC1) Esbjerg's record: 1 source page and 1 recorded deal - enter work email
Sign in to see where it sits on the map, every source page and each figure with the page and quote it comes from.
2024 vs 2026 satellite construction check
Dated 10 m satellite passes are stored for Dansk Data Center 1 (DDC1) Esbjerg (29 April 2024 to 7 November 2026) for before-and-after comparison in the workspace.
Open 2024 vs 2026 satellite slider · All Europe 2024 vs 2026 satellite-tracked sites
Other data centers in Denmark
- atNorth DEN02 Varde
Varde, Denmark, planned250 MW - atNorth DEN01
Ballerup, Denmark, operating22.5 MW - Vaultica COP01A
Copenhagen, Denmark, operating1.2 MW - Bulk DK01 Esbjerg Campus
Esbjerg, Denmark, operatingNot recorded - Copenhagen CPH-RS
Valby, Denmark, operatingNot recorded - Copenhagen CPH1
Ballerup, Denmark, operatingNot recorded
Full site dossier & Europe dataset
Open Dansk Data Center 1 (DDC1) Esbjerg and 500 other data centers
This page is the public summary for Dansk Data Center 1 (DDC1) Esbjerg in Esbjerg, Denmark. Sign in to see its full record: 1 source page and 1 recorded deal.
- Dansk Data Center 1 (DDC1) Esbjerg on the interactive map, with the sites around it
- All 1 linked source page
- 1 recorded deal on this site
A subscription opens full site-level data; the 3-day preview shows 20 sites. Instant sign-in with no password.
Free weekly market briefing
Not ready for the preview? Get the weekly email update
Once a week: new deals, primary filings and capacity changes recorded in this market. Free, with one-click unsubscribe.
Questions
Who operates Dansk Data Center 1 (DDC1) Esbjerg?
Dansk Data Center 1 (DDC1) Esbjerg is recorded under Thylander. The operator is the name its sources give, which can differ from the owner or the tenant.
Where is Dansk Data Center 1 (DDC1) Esbjerg?
In Esbjerg, Denmark. This page does not publish a street address or map coordinates; the workspace shows the location on the map.
How much power does Dansk Data Center 1 (DDC1) Esbjerg have?
11.5 MW, as stated by DCD. The site is not operating yet, so this is a stated plan, not delivered capacity. Operating capacity today is not recorded.
Is Dansk Data Center 1 (DDC1) Esbjerg under construction or growing on satellite imagery?
Dated 10 m satellite passes are stored for Dansk Data Center 1 (DDC1) Esbjerg (29 April 2024 to 7 November 2026) for before-and-after comparison in the workspace.
Where does this information come from?
From 1 linked page by DCD. Every link on this page goes to the original page. Anything not published there shows as not recorded, never as an estimate.