Grid headroom, BTM power & operator 10-K benchmarks
United States data centers:grid headroom, BTM power and 10-K filings.
US ISO grid reserve headroom fell from 70.2 GW (2021) to 15.9 GW (2026) while behind-the-meter power orders hit 75 GW. Sourced campus & grid benchmarks. Updated 2026-11-19.
Cumulative BTM gas orders vs. ISO headroom
Bar width shows cumulative behind-the-meter power orders (GW) as grid reserve buffer narrows.
- 2021
Healthy Surplus (+70.2 GW)1.5 GW BTM
+70.2 GW headroom - 2025
74% Buffer Collapse (+18.3 GW)32 GW BTM
+18.3 GW headroom - 2026
Razor-Thin Buffer (+15.9 GW)75 GW BTM
+15.9 GW headroom - 2030 (forecast)
Structural Deficit (-40.0 GW)145 GW BTM
-40 GW headroom
Largest behind-the-meter AI campuses (MW)
On-site gas turbine, fuel-cell, and co-located generation programs tracked in Real Assets.
- US BTM Supply Chain Orderbook (Total)
All US AI Labs & Hyperscalers · US-Wide (ERCOT / PJM / MISO / WECC)75GW firm orders (~20GW in Q2 2026) - Microsoft Behind-the-Meter Gas Portfolio
Microsoft · TX / WI / Mid-Continent ISOs5GW nameplate (2.7GW + 2GW) - Google Armstrong TX & Cheyenne WY Campuses
Google · Armstrong Co., TX & Wyoming930MW turbines + 900MW fuel cells - OpenAI Stargate Shackelford Flagship (Off-Grid)
OpenAI / Vantage · Shackelford County, TX1.4GW Shackelford + 1.3GW New Mexico - xAI Colossus 2 Memphis / Mississippi Turbine Array
xAI · Memphis, TN / Southaven, MS1.2 GW plant + 150MW Megapacks - Anthropic & Meta High-Speed V12 Genset Deals
Anthropic & Meta · OH / IN / LA Campuses300-500MW deals + 1.5GW off-grid
US ISO grid headroom trajectory (2021 to 2030)
| # | Year & milestone | Reserve status | ISO headroom | BTM orders | Source |
|---|---|---|---|---|---|
| 1 | 2021 Pre-AI US ISO Effective Reserve Headroom | Healthy Surplus (+70.2 GW) | +70.2 GW | 1.5 GW | Source |
| 2 | 2025 51.9 GW of US Grid Headroom Consumed in 4 Years | 74% Buffer Collapse (+18.3 GW) | +18.3 GW | 32 GW | Source |
| 3 | 2026 75 GW of Firm BTM Gas Orders Triggered (~20 GW in Q2 2026 Alone) | Razor-Thin Buffer (+15.9 GW) | +15.9 GW | 75 GW | Source |
| 4 | 2030 (forecast) Aggregate US ISO Grid Deficit Reaches ~40 GW by 2030 | Structural Deficit (-40.0 GW) | -40 GW | 145 GW | Source |
Tracked behind-the-meter (BTM) US data center deployments
| # | Campus & OEM equipment | Hyperscaler / operator | Location | Power capacity | Prime mover configuration | Source |
|---|---|---|---|---|---|---|
| 1 | US BTM Supply Chain Orderbook (Total) GE Vernova, Mitsubishi, Siemens, Jenbacher, Solaris, Caterpillar, Bloom Energy, ERock | All US AI Labs & Hyperscalers | US-Wide (ERCOT / PJM / MISO / WECC) | 75GW firm orders (~20GW in Q2 2026) | 75 GW firm binding BTM orders (~3 GW operational BTM IT by YE 2026) | Source |
| 2 | Microsoft Behind-the-Meter Gas Portfolio Joulent, Chevron, GE Vernova (7HA Heavy-Frame & Aeroderivatives) | Microsoft | TX / WI / Mid-Continent ISOs | 5GW nameplate (2.7GW + 2GW) | >5 GW BTM nameplate gas generation; 2.7 GW co-developed with Joulent & Chevron | Source |
| 3 | Google Armstrong TX & Cheyenne WY Campuses Bloom Energy (900 MW SOFC), Mitsubishi Power (>1 GW J-Class), GE/Baker Hughes | Armstrong Co., TX & Wyoming | 930MW turbines + 900MW fuel cells | 930 MW off-grid aeroderivative turbines (Armstrong TX) + 900 MW Bloom SOFC Fuel Cells & >1 GW Mitsubishi J-Class (WY) | Source | |
| 4 | OpenAI Stargate Shackelford Flagship (Off-Grid) INNIO Jenbacher (J624 2-Stage Turbocharged Reciprocating Engines) | OpenAI / Vantage | Shackelford County, TX | 1.4GW Shackelford + 1.3GW New Mexico | 500+ × 4.25 MW INNIO Jenbacher J624 reciprocating gas engines | Source |
| 5 | xAI Colossus 2 Memphis / Mississippi Turbine Array Solaris Energy Infrastructure, Caterpillar Solar Turbines, Tesla Megapack | xAI | Memphis, TN / Southaven, MS | 1.2 GW plant + 150MW Megapacks | 41-turbine 1.2 GW permanent plant in Mississippi + 150 MW Tesla Megapack buffer | Source |
| 6 | Anthropic & Meta High-Speed V12 Genset Deals ERock (0.5 MW 21.9L V12 Containerized Gas Gensets) | Anthropic & Meta | OH / IN / LA Campuses | 300-500MW deals + 1.5GW off-grid | 600-1,000 units per lab of 0.5 MW gensets built on 21.9-liter V12 natural gas engines | Source |
| 7 | Oracle Project Jupiter (NM) & Bloom Fuel-Cell Orders Bloom Energy (Solid-Oxide Fuel Cells) | Oracle / OpenAI & Nebius | Doña Ana Co., NM & Vineland, NJ | 3.8 GW Bloom fuel-cell bookings | 3.8 GW of solid-oxide fuel cell bookings; 2.45 GW Project Jupiter microgrid | Source |
Listed data center operators: what their filings report
| # | Operator & ticker | Portfolio scale | Occupancy | Revenue & NOI | Pricing & same-store | Debt & leverage | Filing |
|---|---|---|---|---|---|---|---|
| 1 | Equinix, Inc. NASDAQ: EQIX | 280 data centers in 77 markets across 36 countries · 500,000+ interconnections · 299,300 cabinets billed in 255 consolidated IBXs | 79% / 76% / 73% cabinet utilization (Americas / EMEA / Asia-Pacific IBX data centers, Dec 31, 2025) | $9,217M FY25 revenue ($8,748M FY24, +5%) | $2,694 / $2,418 / $2,355 MRR per cabinet (Americas / EMEA / Asia-Pacific) | ~$21.4B total indebtedness incl. finance lease liabilities (Dec 31, 2025) | FY 2025 |
| 2 | Core Scientific, Inc. NASDAQ: CORZ | 10 data centers in 7 U.S. states · ~1.4 GW gross utility power capacity · ~920 MW total leasable customer power capacity | 590 MW leased customer power capacity (330 MW unleased) · 120 MW billable at December 31, 2025 | $319.0M total revenue (FY 2025; $510.7M in 2024) · $65.4M colocation revenue | Fixed monthly colocation fees on billable customer power capacity; power passed through to customers without markup | ~$1.09B indebtedness for borrowed money · $460.0M 3.00% Convertible Senior Notes due 2029 · $625.0M 0.00% notes due 2031 | FY 2025 |
| 3 | Applied Digital Corporation NASDAQ: APLD | 400 MW Polaris Forge 1 campus in Ellendale, ND (100 MW and 150 MW buildings under construction) · ~286 MW Data Center Hosting (Jamestown 106 MW, Ellendale 180 MW) | Two leases signed May 28, 2025 for the first two Polaris Forge 1 buildings, totaling 250 MW | $142.3M revenue (FY 2025, up 17% from $121.9M) | HPC Hosting: long-term leases of approximately 15 years; Data Center Hosting: anchor tenants on 3-5 year contracts, the rest on 18-36 month terms | HPC Hosting Business unit purchase agreement with Macquarie Asset Management, closing subject to conditions | FY 2025 (year ended May 31, 2025) |
| 4 | Digital Core REIT SGX: DCRU | 11 freehold data centres in core global markets · US$1.8B assets under management | 97% portfolio occupancy (in-service portfolio) · 4.6-year weighted average lease expiry | US$176.2M gross revenue · US$88.7M Net Property Income · 3.60 US cents DPU | 7.06% distribution yield (FY 2024: 6.21%) | 37.1% aggregate leverage (FY 2024: 34.0%) · 3.5% weighted avg cost of debt · 85% fixed-rate debt | FY 2025 |
| 5 | Anthropic, PBC SEC S-1/A: ANTH | $900.9B aggregate compute & infrastructure commitments, including $451.2B of uncommenced data center & equipment leases · $313,819M purchase commitments | $161.2B Broadcom equipment finance leases · $121.3B Google Cloud TPU minimum (plus an estimated $125.0B to $150.0B more) · up to $120.5B SpaceXAI (cancellable on 90 days notice after Jan/Mar 2027) | $33,242M 9M 2026 revenue ($16,956M Q3 2026; $4,585M FY 2025) · $18,808M 9M 2026 compute & infrastructure expense | $110.0B Amazon / AWS minimum · $47.2B-$49.2B Microsoft · up to $44.6B Nscale · $41.3B Lambda ($34.9B August agreement currently terminable by either party) · AMD Helios: no fixed amount (more than $20.0B if procured in full) | $95.6B cash & cash equivalents · $6.2B Amazon rollover notes · $77,000M undrawn NPA facilities ($42.0B Broadcom, $20.0B Google, $15.0B Amazon) | Q3 2026 (as of Sep 30, 2026) |
Accounting & reporting methodology contrasts across filings
| # | Dimension & operators | Reporting contrast | Filing rule & reconciliation |
|---|---|---|---|
| 1 | Retail Cabinet MRR vs. Wholesale $/kW vs. AI Retrofit Credits Equinix (EQIX) · Core Scientific (CORZ) · Digital Core REIT (DCRU) | Equinix ($2,355-$2,694/cabinet MRR) vs. Wholesale Colocation ($145 to $200/kW/mo, Avison Young) vs. Core Scientific HPC | Equinix bills per cabinet (~4-8 kW average retail density plus fees on 500,000+ interconnections). Wholesale REITs (Digital Core REIT) lease powered shell/turn-key halls by critical IT MW, while Core Scientific charges fixed monthly fees on billable customer power capacity and passes power through without markup. |
| 2 | Gross Utility Megawatts vs. Critical IT Megawatts Core Scientific (CORZ) · Applied Digital (APLD) | ~1.4 GW Gross Utility Power vs. ~920 MW Leasable Customer Power (Core Scientific, December 31, 2025) | AI neocloud filings (Core Scientific, Applied Digital) frequently headline gross utility substation capacity (MW) alongside critical IT load (MW) delivered to GPU racks. Always check whether the denominator is utility transformer capacity or post-PUE IT load. |
Extracted SEC & exchange filings corpus
| # | Company & filing title | Type | Period | Facts | Key disclosures | Source |
|---|---|---|---|---|---|---|
| 1 | Anthropic, PBC (ANTH) Anthropic, PBC Form S-1/A (Amendment No. 2 to Registration Statement, Q3 2026) | S-1/A | FY 2023 to Q3 2026 | 19 | $900.9B aggregate compute and infrastructure commitments across Broadcom ($161.2B), Google Cloud ($121.3B, plus an estimated $125B to $150B more), SpaceXAI (up to $120.5B), Amazon ($110.0B), Microsoft ($47.2B to $49.2B), Nscale (up to $44.6B), Lambda ($41.3B), and AMD (no fixed amount; more than $20.0B if procured in full), plus quarterly statements of operations through Q3 2026 ($16,956M quarterly revenue). | Open |
| 2 | Equinix, Inc. (EQIX) Equinix, Inc. Form 10-K (FY 2025) & Q2 2026 Form 8-K Earnings Release | 10-K / 8-K | FY 2025 to Q2 2026 | 120 | Americas, EMEA, and APAC IBX cabinet billing, interconnection counts, xScale hyperscale JV capacity, AFFO per share, and debt maturity schedule. | Open |
| 3 | Digital Core REIT (DCRU) Digital Core REIT Annual Report 2025 & 1H 2025 Financial Statements | Annual Report | FY 2025 | 79 | Asset-by-asset valuation, IT MW capacity, occupancy, WALE, and NPI across Northern Virginia, Silicon Valley, Los Angeles, Toronto, Frankfurt, and Osaka. | FY 2025 |
| 4 | Applied Digital Corporation (APLD) Applied Digital Corporation Form 10-K (FY 2025) | 10-K | FY 2025 | 48 | Ellendale 400 MW AI HPC campus construction, cloud GPU cluster deployment, and project-level financing disclosures. | Open |
| 5 | Core Scientific, Inc. (CORZ) Core Scientific, Inc. Form 10-K (FY 2025) | 10-K | FY 2025 | 42 | Site-by-site U.S. megawatt allocations across Texas, North Dakota, Georgia, North Carolina, Kentucky, and Oklahoma, and 590 MW CoreWeave HPC lease terms. | Open |
Full market dataset & site-level records
Open the interactive United States data centers research workspace
Inspect all 1,369 tracked sites, source PDFs, and interactive exhibits inside Real Assets.
- Every individual site on the interactive map with coordinates
- Operating vs. pipeline capacity, operator and owner records
- Sourced M&A, lease and financing transactions
- Direct link to the filing, report or news page behind every figure
- Ask Real Assets from ChatGPT, Claude and Claude Code: connect it from your account after you sign in
A subscription opens full site-level data; the 3-day preview shows 20 sites. Instant sign-in with no password.
Free weekly market briefing
Not ready for the preview? Get the weekly email update
Once a week: new deals, primary filings and capacity changes recorded in this market. Free, with one-click unsubscribe.
Questions
Why are US data centers turning to behind-the-meter (BTM) power?
Gross positive grid reliability headroom across US ISO territories fell from 70.2 GW in 2021 to 18.3 GW in 2025 and 15.9 GW in 2026, while interconnection queues stretched to 5 to 8 years. AI campus developers placed roughly 75 GW of cumulative firm BTM power equipment orders by 2026.
When is US ISO grid headroom projected to turn negative?
Published ELCC reserve models tracked in Real Assets project net US ISO headroom turning negative in 2027 and reaching an aggregate deficit of roughly 40 GW by 2030.
Where do the US grid and BTM deployment figures come from?
Every benchmark row links to its original published source, utility filing, or SEC Form 10-K/10-Q as of 2026-11-19.